Global AI assets are undergoing a shift in investment logic.
From Nvidia and AMD to CoreWeave and Nebius, Wall Street has begun to ask: how can the computing power that has already been built continue to generate value?
This shift is not confined to U.S. equities. Hong Kong stocks have also recently reached a revaluation point, and the market's scrutiny of asset quality and commercialization capability has clearly become stricter.
Yet between chip manufacturers and model developers, AI infrastructure companies—acting as schedulers and distributors in the computing power supply chain—are accelerating toward the IPO market.
As several companies have filed successively, the business models of the middle layer of AI infrastructure have for the first time been presented collectively to Chinese investors. Among them, Jiuzhang Cloud has taken the "new intelligent computing cloud" path: developing its own intelligent computing operating system and computing power metering system downstream, while providing intelligent computing cloud services upstream. Along this path, every efficiency variable—from computing power resources to customer delivery—will directly show up in the financial statements.
Behind this acceleration of capitalization, how should the commercial value and growth potential of AI infrastructure companies be understood? Financial statements are the most direct entry point, and to open this door, one must first understand the leverage embedded in the operating structure of the new intelligent computing cloud.
In the revaluation of AI infrastructure, why is the efficiency of the new intelligent computing cloud the focus?
"Stockpiling cards" was the keyword in the construction of global intelligent computing centers over the past two to three years. Following the early expansion inertia of hardware infrastructure, scale was once everything.
According to Caixin statistics, capital expenditure by the six major U.S. cloud vendors rose from $251.6 billion in 2024 to an expected $871.1 billion in 2026, with its share of U.S. GDP rising from 1.4% to 2.7%.
With capital expenditure expanding at such a slope, it has become an independent variable affecting macroeconomic liquidity and the industrial landscape—and it is only natural that the market's demand for returns has increased.
At this stage, investors inevitably need to study in depth the return capacity of the entire AI industry chain, and in doing so they will discover the critical position of the new intelligent computing cloud.
In this round of AI infrastructure expansion, the funding entities and the operating entities are separate. According to the classification by the China Academy of Information and Communications Technology, chip manufacturers focus on making chips, cloud vendors and AI companies focus on model and application innovation, and the construction, scheduling operations, and stable delivery of GPU clusters are undertaken by the new cloud.
The new intelligent computing cloud actually refers to a position: between computing hardware and models, it undertakes the organization, metering, and delivery of computing power. To judge whether a company occupies this position, there are two criteria: whether it can turn reserved computing power into measurable, deliverable services, and whether it has controllable computing power.
Fang Lei, founder, chairman, and CEO of Jiuzhang Cloud, said that the value of computing power lies not in stacking resources, but in the delivery of capabilities.
Viewed more broadly, the new cloud sits at the hub of the formation and monetization of computing power assets. The level of asset operating efficiency in the financial statements is a concentrated reflection of the asset quality of the entire industry chain.
In this regard, the market has already formed a new set of financial statement evaluation language.
Referring to the two major new cloud companies in U.S. stocks, as of the end of June 2026, CoreWeave's revenue backlog was approximately $104 billion, corresponding to 3.7 GW of contracted power capacity; Nebius disclosed in its shareholder letter that the annual contract value per megawatt of newly signed large orders has exceeded $20 million, and based on revenue recognition, the payback period for early capital investment is about 1 year and 10 months.
Annual contract value per megawatt dilutes heavy assets into the smallest unit of measurement, while the correspondence between revenue backlog and contracted power capacity tests whether orders can be converted into real production capacity.
Wall Street generally recognizes that to bypass scale and directly measure efficiency, attention should be paid to the organization and integration capability of underlying resources.
The valuation logic of Hong Kong stocks is undergoing a similar change.
Whether on the capital side or the industrial side, thinking has shifted from looking at concepts and listening to stories in the past to focusing on real business progress and commercialization capability.
In an environment where standards on both the funding side and the regulatory side have been raised, investors need to study in depth the composition of the operating leverage of China's new cloud companies and whether it is being continuously improved.
Leveraging operating leverage to transform efficiency premiums into profit elasticity
The operating structure of the new intelligent computing cloud has leverage characteristics.
According to the industry's common cost structure, hardware depreciation accounts for about 40% to 50% of total costs, electricity accounts for 10% to 20%, bandwidth and operations and maintenance about 10%, and labor about 10%.
Depreciation is fully accrued from the time equipment is put into use, forming the main body of fixed costs, and equipment still depreciates even when idle. Revenue, meanwhile, is recognized based on actually delivered computing power and fluctuates with task volume.
Therefore, the profit of the new intelligent computing cloud is elastic with respect to revenue, and there are three switches for improving operating leverage:
The first switch is obviously utilization.
Since equipment depreciation is unrelated to usage intensity, every increase in utilization dilutes pure fixed costs.
Based on a static calculation using data disclosed in Jiuzhang Cloud's prospectus, the utilization rate of computing resources rose from 56.0% in 2025 to 79.6% in the first half of 2026. Under static assumptions that equipment scale and total depreciation remain unchanged and effective output grows synchronously with utilization, the depreciation cost allocated per unit of effective computing power can fall to 56/79.6 of the original, that is, a theoretical reduction of about 29.6%. This calculation does not include variable costs such as electricity, nor does it mean that the actual financial statements have already realized a cost reduction of the same magnitude.
Improving utilization mainly depends on engineering capability—for example, through unified scheduling of heterogeneous computing power and training-inference orchestration. This is also where Jiuzhang Cloud's computing resource utilization has room to improve. According to Jiuzhang Cloud's prospectus, at the scale of 504 intelligent computing accelerators and 63 nodes, a 30-day continuous production run achieved 54.1% MFU, equivalent to about 535 TFLOPS per accelerator, with daytime MFU fluctuation of only 1.60%. According to CIC Consulting, this sustained efficiency is significantly higher than the industry average under comparable parameter scales.
In addition, the optimization of fixed costs also comes from the gap time between new equipment being powered on and generating revenue. Jiuzhang Cloud's automated cluster deployment replaces traditional network boot processes with a virtualized disk and network interface architecture, shortening the expansion time of a thousand-node cluster by more than 85% and increasing node configuration speed by more than 7 times. New computing power enters the task process faster after being connected, and the idle period of fixed assets is compressed.
The second switch is energy consumption.
Electricity is the fastest-growing item in the operating costs of intelligent computing centers: an H100 cluster at the scale of 100,000 cards has power consumption exceeding 150 MW, annual electricity use of about 1.6 billion kWh, and electricity bills in the hundreds of millions of dollars. Electricity's share of operating costs has risen from about 30% five years ago to 40% to 50%.
The new cloud can optimize energy consumption from the computing level. Parameter synchronization is the largest source of idle operation in distributed training; every fewer data pass saves both energy and waiting. Through network-layer engineering, Jiuzhang Cloud's in-network computing and rail-optimized interconnect double All-Reduce performance, halve data traffic, and achieve network bandwidth utilization exceeding 95%.
The third switch acts on the way assets are formed.
The early model of the new cloud was mainly purchasing cards and building data centers, which was a heavier model. Now companies are leveraging lighter methods.
In July 2026, Nebius launched a partner model in which partners hold the hardware, while the company provides system architecture, software stack, and customer orders, with revenue shared according to agreement.
Jiuzhang Cloud also offers a new solution: intelligent computing centers are funded and built by external partners, while the company outputs architecture design, hardware deployment, and daily operations. Reflected in the financial report, as of the end of June 2026, the net value of property, plant, and equipment was only 71.7 million yuan, while the controllable computing power scale reached 26,824 PFLOPS. The essence of being asset-light is that input is reflected in usage rights rather than ownership—shifting from holding assets to operating assets.
It can be seen that the new intelligent computing cloud is improving operating leverage at various levels, and the high fixed-cost structure determines the form of realization, namely reversibility.
Nebius's adjusted EBITDA margin for its AI cloud business rose from 24% in the fourth quarter of 2025 to 50% in the second quarter of 2026, doubling in three quarters.
In the first half of the year, Jiuzhang Cloud's overall gross margin rose from 18.4% in the same period last year to 31.0%, the gross margin of core intelligent computing cloud services turned positive from negative, and after excluding non-cash effects such as share-based payment and changes in the fair value of preferred shares, the adjusted loss narrowed by 75.2% year on year.
Obviously, as operating leverage is released, the marginal cost of incremental revenue drops significantly. Amid the dual rhythm of breakthroughs in its own engineering capability and the industrialization of AI, the new intelligent computing cloud has provided the capital market with preliminary verification regarding returns.
Future growth space is still worth anticipating.
From engineering evolution to platform services, the scale of AI applications determines long-term value space
Along with the evolution of the new cloud's own engineering capability, the industrialization of AI is also accelerating.
In AI industrialization, the focus of computing power demand is shifting from training to inference, where demand is higher. Gartner expects that in 2026 global AI inference spending will exceed training spending for the first time.
However, inference places new requirements on infrastructure.
Training workloads are concentrated, large in scale, and long in cycle; a single task can occupy an entire cluster for months. Inference workloads are the opposite: dispersed, fragmented, and highly elastic, with task durations ranging from milliseconds to hours, and demand for single cards and entire clusters appearing alternately.
The direction of the new cloud companies' engineering investment over the past few years—including unified scheduling of heterogeneous computing power, training-inference orchestration, automated deployment, and network-layer optimization—has all been aimed at efficiently matching fragmented demand with heterogeneous computing power.
This is also a manifestation of the new cloud's position at the hub of the formation and monetization of computing power assets, gaining insight into industry demand and growing in sync with demand.
According to CIC Consulting data, the scale of China's inference service market will grow from 53.6 billion yuan in 2025 to 226.1 billion yuan in 2030, with a compound annual growth rate of 36.3%, and its share in intelligent computing services will rise from 48.1% to 81.5%.
Behind the expected continued growth of intelligent computing services is a wave of inclusive computing power.
In the computing power field, the Jevons effect is significant: every decrease in price expands the range of use cases. In the training era, only leading companies could afford computing power; in the inference era, application developers and small and medium-sized enterprises have become the source of new demand, and demand is penetrating downward along the ladder of cost-effectiveness.
At the same time, changes in demand are also reshaping the form of competition.
The fragmented and highly elastic nature of inference workloads determines that competition in the new intelligent computing cloud is shifting from resource supply to service capability. Only by encapsulating computing power into on-demand services and model capabilities into deliverable products can this downward-penetrating demand be captured.
Leading companies in the industry have already formed stable delivery capabilities and are evolving upward along the levels of computing power resource services, model capability services, and AI engineering services—connecting more computing power resources and partners upstream and reaching more developers and small and medium-sized enterprises downstream.
Looking ahead, platform-based and service-oriented new intelligent computing clouds will become a key variable in accelerating the AI industry process.
According to a McKinsey report, by 2030, total AI demand will increase from 120 GW to 278 GW, and the long-term development of new cloud vendors needs to extend toward AI-native services.
From building computing power to enhancing resource efficiency through engineering capabilities, and then to scaling platform services and AI applications in the future, the longer-term value potential of this round of infrastructure investment is beginning to unfold.
Source: Hong Kong Stock Research Society